CONSTRUCTION OF A BULK HANDLING BERTH No.10 - YANBU PORT - SAUDI ARABIA

The location of the project was the Commercial Port of Yanbu in Kingdom of Saudi Arabia. The main scope of the project consisted on the underwater embankment construction on a volume of 105.000 m3, the underwater construction of crushed stone layer on 13.500 m2 surface, and the laying of 1100 concrete blocks with total weight between 90 to 170 tons.

The project’s duration was 24 months